Mining, oil & gas

LINDERO

Salta

Lindero is a mining project located in the province of Salta of the company Mansfield Minera S.A. belonging to Fortuna Silver Mines Inc. Panedile executed the civil works of soil movement and concrete in the initial stage of the project.

Civil works for a mining project 3,800 meters above sea level

8,938,09 m3
Concrete
303,970 m3
Earthworks
3,800 m
above sea level

PROJECT

Civil Works for the Lindero Project

CLIENT

Mansfield Minera S.A-Proyecto Lindero

DESCRIPTION OF WORK

Panedile was responsible for executing earthworks (such as leveling, excavation, filling and compaction) and pouring all the concretes (cleaning, foundations, retaining walls, floor slabs and support structures) of the Lindero Project. Located in the Los Andes district in the province of Salta, 430 km southwest of the provincial capital city, the gold mine lies just off the road leading up to the Socompa Pass on the Chilean border.

 

Earthworks     

Embankment: 110,910 m3          Clearance: 151,820 m3                Gravelling: 11,900 m3                  Antifreeze base: 14,670 m3        Drainage subbase: 14,670 m3   

TOTAL:  303,970 m3

Concrete

Cleaning concrete H-8: 180.09
Reinforced concrete beams H-20: 205.11
Reinforced concrete pillars and columns H-25: 250.42
Reinforced concrete base H-20: 3,788.09
Reinforced concrete slabs H-20: 441.48            Reinforced concrete walls and dividers H-20: 510.44        Reinforced concrete flooring H-15: 3,562.46
TOTAL:  8,938.09